Project Timetable
March 1999
Artists and School Grounds seminar organised
by artist Hattie Coppard for Primary Schools
in Hackney Wick
June 1999
Publication Artists and School Grounds
circulated free to 80 schools in Hackney.
December
1999
Hattie Coppard appointed to undertake consultation
and development work on Daubeney Primary
School playground with funding from SRB budget.
March
2000
Experimental Playground Week takes place at Daubeney
Primary School.
September 2000
Kinnear Landscape Architects contracted
to work with Hattie Coppard on design of playground
using findings of Experimental Playground Week.
November 2000
Presentation by Hattie Coppard and
Lynn Kinnear of ideas/findings to teachers, governors,
pupils and parents.
March 2001
Design proposals formulated – presented
as public exhibition and range of opportunities for
teachers/pupils to respond to proposals.
April 2001
Designs worked up into final details and
specifications. Fundraising for capital works through
National Lottery/Grounds for Change.
June 2001
Evaluation Study by Eileen Adams published
on Experimental Playground.
July 2002
Capital scheme put out to tender – Baylis
awarded contract.
September 2002
Work commenced on site – Construction
Phase I.
April 2003
Construction Phase II and completion of
capital works.
June 2003
Celebrations at school: residencies by dancer and poet.
July 2003
Formal opening of playground
Evaluation on use of the Playground undertaken
by New Economics Foundation and the school as an ongoing project.